Be sure to attend our next PTO Meeting on Monday, February 6, at 6 p.m. in the Library. Representatives will be there to share more information about the new Hazeldale School building!
A few additional facts about the new school, which will be the largest K-5 school in the district, per the Beaverton School District website:
- 87,200 square feet (31,356 SF increase; +44%)
- No proposed Portables
- 32 classrooms, plus 9 additional teaching spaces, including 5 flex commons, stage, teaching area in the library, and dividable gym supporting 2 simultaneous PE classes
- Gym 6,717 square feet (+61% increase)
- Cafeteria 3,705 square feet (+5% increase)
- 150 parking stalls including special event parallel parking spaces (+55% increase)
- 10,000 square foot covered play area (+31% increase)
- Walk/Run path (new)